QUALITY CONTROL

Can complete: equipment thermal field verification, continuous operation durability testing, process curve verification, customer customized process experiments

1. Establishment of Quality Management System

According to the standard:

Development of PLC Control System

Optimization of PID temperature control algorithm

Remote monitoring system

MES docking interface development

 

Develop documents:

Quality Manual

Program file

Standard Operating Procedure (SOP)

Inspection specifications (IQC/IPQC/FQC/OQC)

1. Establishment of Quality Management System

2. Quality Control Process

01
Sales technical confirmation
02
Design Review
03
Raw Material Inspection (IQC)
04
Production Process Control (IPQC)
05
Whole machine debugging and testing (FQC)
06
Factory Acceptance (OQC)
07
Customer on-site installation acceptance
08
After sales quality tracking

3. Detailed Quality Control Process

Sales+Technology+Production Tripartite Review

 

Clearly state the following:

Furnace type specifications

maximum temperature

temperature control accuracy

Atmosphere requirements (hydrogen/nitrogen/mixed gas)

load weight

degree of automation

Safety Standards (Exporting Countries)

Key Control Points: Preventing Rework

Structural Strength Calculation

Heating Power Matching

Insulation Material Selection

Control System Logic Review

Electrical Safety Review

 

Mandatory Procedures:

Three-Level Review of Design Drawings (Designer → Technical Supervisor → Chief Engineer)

FMEA Analysis (Failure Mode and Effects Analysis) for Key Equipment

Inspection Objects:

Furnace shell steel plate

Heating elements (heating wire/heating tube)

Refractory materials

Stainless steel plate

PLC control system

Frequency inverter

Temperature controller

 

Inspection Method

Item Inspection Content
Appearance Deformation and rust check
Dimension Thickness and specification check
Material Material certificate verification
Electrical Components Brand and model confirmation

 

Non-conforming product isolation and handling;

Supplier quality rating management

Welding Quality Control

Weld Appearance

Weld Penetration Testing

Air Tightness Testing

 

Furnace Assembly Control

Insulation Layer Thickness

Heating Element Arrangement

Furnace Chamber Coaxiality

 

Electrical System Control

Wiring Specifications

Grounding Resistance Testing

Insulation Resistance Testing

PLC Logic Simulation Operation

👉 Signature Confirmation for Each Process

👉 Video Recording of Key Processes (Recommended for Export Equipment)

Empty furnace heating test

Full load test

Temperature control accuracy test

Furnace temperature uniformity test (±5℃ or customer requirements)

Alarm system test

Air tightness test

48-hour continuous operation test

👉 Issuance of a "Factory Inspection Report"

Visual inspection

Paint thickness inspection

Nameplate verification

Random document list confirmation

Packaging rust prevention treatment

👉 Customer video acceptance (Recommended for export)

Provide installation instructions

Remote commissioning support

Operating data recording

Customer satisfaction follow-up

Closed-loop handling of quality issues

01
Contract and Technical Confirmation
02
Design quality control
03
Raw material quality control
04
Critical control point
05
Required test items
06
Final Quality Control (OQC)
07
Installation and After-sales Quality Control

4. Key points of quality risk control

Risk Points

Control Methods

Uneven Temperature

Add Multi-Point Thermocouple Detection

Air Leakage

Weld Seam Air Tightness Test

Short Heating Element Lifespan

Select High-Quality Materials

Control System Failure

Uses well-known brand PLCs

Export Returns

Enhanced Debugging and Testing

Suggestions for Quality Data Management

5. Suggestions for Quality Data Management

Establish MES system

Establish a record file for key equipment

Establish an after-sales fault database

Regular quality analysis meetings

6. Upgrade suggestion

Passed ISO9001 certification

Through CE

Create a third-party testing report

Key equipment video archiving

Provide FAT (Factory Acceptance Test)

Upgrade suggestion

TESTING EQUIPMENT

Can complete: equipment thermal field verification, continuous operation durability testing, process curve verification, customer customized process experiments

Testing Equipment
Testing Equipment
Testing Equipment
Testing Equipment
Testing Equipment
Testing Equipment
Testing Equipment
Testing Equipment

CERTIFICATIONS

Can complete: equipment thermal field verification, continuous operation durability testing, process curve verification, customer customized process experiments

Certificate Name

Certificate Name

Do You Have Any Questions?

If you are interested in any of our products or would like to make your customized order, please feel free to contact us. We are looking forward to establish successful business relations with you.