Mesh Belt Furnace Throughput: Calculate Parts/h and kg/h

Mesh Belt Furnace Throughput: Calculate Parts/h and kg/h

Nov. 20, 2026

Share:

A mesh belt furnace capacity quoted in kg/h is useful only when the part, loading arrangement and treatment conditions are defined. Two proposals can show the same hourly output while assuming different products or operating schedules.

Start by separating the amount conveyed into the line from the amount of acceptable product delivered. The calculations below help buyers prepare a capacity discussion. They do not establish a furnace's thermal capability or replace a production trial.

What Does the Quoted Furnace Capacity Include?

Ask whether kg/h means incoming workpiece mass, total conveyed mass including carriers, or accepted finished-product mass. If parts lose mass during processing, define which weighing stage applies. Record parts per hour as well when purchasing equipment for a specific component.

Next, identify the conditions attached to the figure: material, treatment, part dimensions, loading pattern and operating speed. A rating for one part family is not automatically applicable to another.

For example, page 5 of SECO/WARWICK's mesh belt furnace brochure presents production capacity alongside processing time and loading information. It explicitly treats the data as indicative and dependent on the application. Its numbers describe that supplier's equipment, not Rexin ratings.

Calculate Parts per Hour from Pitch and Lane Count

For a continuous belt carrying regularly spaced, discrete parts, define the longitudinal pitch as the distance from a reference point on one part to the corresponding point on the next part in the same lane. Pitch includes the part's length in the travel direction and the gap after it.

When speed and pitch use matching length units, the geometric feed rate is:

Parts/h = belt speed (m/min) ÷ longitudinal pitch (m/part) × number of lanes × 60.

This expression assumes one part at each pitch position in every lane, continuous movement and no empty positions. For a carrier holding several parts, count carrier positions first and multiply by the actual parts per carrier. Do not count the same parts again as separate lanes.

Lane count must come from an approved loading drawing. Part width, fixtures, lateral spacing and the permitted usable belt width all matter. Bulk layers or irregular loading need a different mass-per-length approach; this discrete-part equation does not describe every loading method.

A Worked Example: Geometric Feed versus Accepted Output

Consider a fictional arrangement with a belt speed of 0.30 m/min, a longitudinal pitch of 0.15 m, three lanes and a workpiece mass of 0.40 kg. Assume the complete arrangement fits the permitted belt envelope.

The calculation gives 0.30 ÷ 0.15 × 3 × 60 = 360 parts/h. Multiplying by 0.40 kg per part gives 144 kg/h of incoming workpieces. These are teaching figures, not recommended settings, a Rexin model specification or a capacity promise.

Now suppose a hypothetical eight-hour production observation records 2,400 accepted parts. The measured accepted output over that window is 2,400 ÷ 8 = 300 parts/h. If each accepted part weighs 0.40 kg, the corresponding accepted-product output is 120 kg/h.

The geometric figure and the measured figure answer different questions. To interpret the difference, examine empty positions, interruptions, start-up conditions and rejected parts. Do not apply a universal percentage reduction or assume every difference is caused by the furnace.

Check Thermal and Mechanical Limits Before Increasing Feed

More loaded positions increase the work entering the process. Before changing the arrangement, have the supplier check the belt and support ratings, clearances, handling equipment and required thermal profile at the proposed loading.

Speed also affects the time available for heating and cooling. The belt-speed discussion in LCI's S-715 process engineering manual, section 5.1, explains this relationship for its infrared furnace. Its specific settings and gas instructions should not be transferred to another furnace design.

The existing continuous annealing process guide explains why residence in a zone is not automatically the same as time at the required workpiece temperature. Validate the material's treatment at the planned loading rather than selecting a faster belt speed solely to reach an output target.

Review the complete line as well. Loading, discharge, cooling, and any specified quenching or washing stages must support the intended production rate. A calculation at the loading station does not prove that accepted parts can leave the full system at that rate.

Compare Proposals with a Capacity Acceptance Worksheet

Use the same definitions for each supplier. Agree how evidence will be collected and which checks require the actual product, fixtures or site utilities.

Item Information to agree Evidence to request
Reference product Material, drawing, dimensions and mass basis Approved part specification and weighing method
Loading arrangement Pitch, lanes, carriers and allowed envelope Loading drawing and demonstration
Process conditions Recipe, atmosphere where required, and planned speed Recorded conditions and product-temperature evidence as agreed
Output definition Incoming parts versus accepted finished parts Separate counts or weights, including rejects
Observation window Duration and treatment of start-up, gaps and interruptions Time log with the calculation denominator stated
Acceptance location Factory demonstration versus site production checks Written test scope, responsibilities and outstanding items

A furnace factory acceptance test checklist can help organize the evidence. A demonstration without representative product conditions should be described accurately, rather than presented as proof of the final production rate.

What Should You Send with a Mesh Belt Furnace Inquiry?

Send the part drawing and material, required treatment, desired accepted output and working schedule. Add a proposed loading drawing, fixture details and available upstream and downstream capacity. List unknowns so they can be resolved during equipment selection.

When reviewing Rexin mesh belt tempering furnace options, ask for a project-specific capacity basis and an agreed verification method. A proposal tied to your actual product and acceptance conditions is easier to compare than an isolated kg/h number.